Cleveland Innerbelt Conceptual Alternatives Study and Request for a "Peer Review" of the Innerbelt Bridge

Submitted by Norm Roulet on Tue, 03/06/2007 - 23:37.

Go "Citizen" Ed Hauser. Doing good to do good, so all may do well! Here is his latest mapping of the landscape of redevelopment of NEO as abstracted by the powers who be to do well for themselves and their friends. Reply requested! I agree with Ed's conclusion:

 CONCLUSION- If our public officials choose NOT to commission the "Peer Review" for the Innerbelt Bridge Project stated above, I recommend a "Minimal Build" alternative for the Cleveland Innerbelt Project.  That would entail straightening the Innerbelt Curve ("Dead Man's Curve") at $98 million and rehabilitate the existing Innerbelt Bridge for 50 years at $268 million for a total cost to the taxpayers of $366 million.  That would save the taxpayers $1.134 BILLION ($1.5B-$366M) that could be used elsewhere.  The citizens and taxpayers of Ohio cannot accept substandard state and federal processes that yield substandard outcomes!

Read Why... 

March 5, 2007
 
To:      James Beasley
            Director, Ohio Department of Transportation
            1980 W. Broad Street
            Columbus, OH 43223
 
From:  Ed Hauser
            11125 Lake Avenue #402
            Cleveland, Ohio 44102
 
Subject: Public Comments for the Cleveland Innerbelt Conceptual Alternatives Study and Request for a "Peer Review" of the Innerbelt Bridge Project - Reply Requested
 
cc:       Federal, State, County, and City Public Officials; Interested Citizens; and the Media
 
Dear Director Beasley:

First of all, I want to congratulate you on your appointment as the director of the Ohio Department of Transportation.  I was pleased to learn about an ODOT transition report and have a renewed hope in ODOT operations with Governor Strickland's and your "new ODOT vision."   The report states, "The Strickland-Fisher Turnaround Ohio plan outlines a new direction for the state that requires ODOT to engage more fully as a partner, to live within its means of available resources and to rethink its role as an agent for change and prosperity for all Ohioans."  

My comments will focus on the Innerbelt Bridge Project, which ODOT has still not revealed to the taxpayers that it will cost $1.16 BILLION.  To put the Innerbelt Bridge Project in perspective:

  1. It is the most costly public works project in the history of Cleveland (Hopkins Runway project is $500 million)
  2. It is over ¾ of the cost for the entire Cleveland Innerbelt Project ($1.5 Billion)

I am sending my comments and request directly to you because ODOT is still moving ahead with its Innerbelt Bridge Project without taking into account its "new ODOT vision."  I understand that the new administration has inherited the Innerbelt Project problems, but we need your leadership get this project under control and do the right thing for Northeast Ohio.  For over one-year I have expressed my concerns about the Cleveland Innerbelt Project by submitting five assessments and numerous letters along with comments at public meetings and at the Section 106 consulting party meetings.

My comments and requests will cover the topics highlighted below:

  • ODOT's Proposed Innerbelt Bridge Plan- Invalid because ODOT is conducting a flawed Project Development Process and Public Involvement Process.
  • ODOT's Proposed Innerbelt Bridge Plan- Demolishes three structures recommended for the National Register of Historic Places.
  • ODOT's Proposed Innerbelt Bridge Plan- $1.168 BILLION Innerbelt Bridge Project is the most costly public works project in the history of Cleveland!
  • Request to Public Officials- It's time to do this right and take responsible action to restore the public's trust and confidence in the State and Federal processes and to use our tax dollars wisely.
  • REQUESTED SOLUTION- Federal, State, County and City Public Officials must commission a "Peer Review" and hire an independent (unbiased) consultant to conduct a valid engineering study and economic impact study to compare the costs, feasibility, traffic interruptions and economic impact for ODOT's Northern Bridge Alignment and the "original" Southern Bridge Alignment (new two-way bridge).

ODOT's Proposed Innerbelt Bridge Plan- Invalid because ODOT is conducting a flawed Project Development Process and Public Involvement Process.

ODOT and the FHWA continue to ignore the major problems with the PDP and PIP after being notified to correct the problems in writing and by public comments.  The result of this inaction will jeopardize the mandated federal process for the National Historic Preservation Act (NHPA) Section 106 process and the subsequent National Transportation Act (NTA) Section 4(f) process, which are part of the overall National Environmental Policy Act (NEPA) Environmental Impact Statement.  Once again, I will highlight several of the major flaws in the PDP and PIP below:

  • The "original" Southern Bridge Alignment Alternative (new two-way bridge) was invalidly removed because ODOT and Burgess & Niple purported that it would take the Greek Orthodox Church in June 2005.  
  • In November 2005, ODOT revised that claim by stating that the Southern Bridge Alignment would encroach on the Tremont Historic District, but never seriously reconsidered that alternative.
  • The original Southern Bridge Alignment Alternative was never fully developed and replaced by a "hybrid" southern alignment with a new East Bound Bridge and keeping the existing bridge.
  • Predetermined outcome for the Northern Bridge Alignment because ODOT began acquiring properties for that bridge alignment in November 2005 (PDP-Step 10) before the federal Section 106 Process began in May 2006 (PDP-Step 4).  ODOT skipped 6 steps of the PDP!
  • Predetermined outcome for the Northern Bridge Alignment because ODOT claimed to have endorsements from public officials on January 21, 2006, prior to the release of the Conceptual Alternatives Study and the evaluation of public comments on the study.  The public comment period for the study remains open until March 5, 2007.  
  • The federal process schedule to inform the public on how and when to participate was released in November 2005.  None of the scheduled items were followed and the schedule was not updated until December 2006.  The public was removed from being involved in the process by not being able to provide any meaningful input while decisions were made concerning the Innerbelt Bridge.
  • ODOT's director wrote a letter in May 2006, acknowledging the "deficient performance" by the lead consultant in several areas but not limited to: leadership; NEPA processes and documentation; documentation and evaluation of alternatives and public involvement meetings; schedule management…
  • The problems stated above clearly demonstrate major flaws in ODOT and federal processes.

 ODOT's Proposed Innerbelt Bridge Plan- Demolishes three structures recommended for the National Register of Historic Places

After reviewing the "Identified Historic Structures with Potential Impacts" display board at the public meeting on February 1, three (3) of the five (5) identified historic structures will be demolished if ODOT implements its "Recommended Preferred Alternative" for the Northern Bridge Alignment.

  • ODOT no longer references or displays any bridge alternatives that will not impact historic structures recommended for the National Register of Historic Places.
  • The flawed processes led to an outcome that will demolish three (3) historic structures without a viable alternative because the Southern Bridge Alignment Alternative was invalidly removed.  
  • Cleveland will lose the historic Broadway Mills Building, Marathon Gas Station and Distribution Terminal Warehouse, which were recommended for the National Register of Historic Places.
  • The federal historic review processes for the NHPA-Section 106 and NTA-Section 4(f) will be jeopardized if ODOT and the FHWA fail to fully develop the "original" Southern Bridge Alignment (new two-way bridge) as an alternative.  That Southern Bridge Alignment Alternative does not impact any structures recommended for the National Register of Historic Places.  
  • These federal processes call for the consideration of all "feasible alternatives" that have the least impact to structures and sites eligible or listed on the National Register of Historic Places.

 ODOT's Proposed Innerbelt Bridge Plan- $1.168 BILLION Innerbelt Bridge Project is the most costly public works project in the history of Cleveland!

On January 31, 2006, I submitted my "Assessment #1 Findings - Request for the FWHA & ODOT to: Correct the Project Development Process & Public Involvement Process and Reconsider the Southern Innerbelt Bridge Alignment Alternative - Reply Requested."  This was the first of five assessments submitted to ODOT and FHWA that were never addressed or replied to.

  • My first assessment concluded by stating, "I will argue that the ODOT "Recommended Preferred Alternative" for the Northern Bridge Alignment will cost us over $1 Billion.  That is because ODOT has not acknowledged the cost to replace the existing bridge in the future."
  • We waited one year and two days (2/1/07) for ODOT to calculate the cost to replace the existing bridge and finally acknowledge that its proposed Innerbelt Bridge Project will cost taxpayers over ONE BILLION DOLLARS for its proposed Northern Bridge Alignment!
  • $1.168 BILLION is ODOT's projected total cost for the Northern Bridge Alignment Project. ODOT's numbers: $1,168,000,000 = $511,000,000 [New Westbound Bridge] + $137,000,000 [Repair Existing Bridge] + $520,000,000 [New Eastbound Bridge].  WOW!  That's a lot of money!
  • The proposed BILLION DOLLAR Innerbelt Bridge Project makes it the most expensive public works project in the history of Cleveland and over 3/4 of the projected cost for the entire Cleveland Innerbelt Project ($1.5 BILLION).  Over twice the cost of the Cleveland Hopkins runway project ($500 million), currently most expensive public works project.
  • ODOT did not provide the cost for the future East Bound Bridge or the entire cost of the Innerbelt Bridge Project to Cleveland City Council or the Cleveland City Planning Commission at the "Innerbelt Update and Overview" meetings in January 2007.
  • No Guarantee that ODOT will fund the future East Bound Bridge for $520 million in 15 years.  ODOT has already begun slashing $1.2 BILLION for major construction projects from its budget.

 Request to Public Officials- It's time to do this right and take responsible action to restore the public's trust and confidence in the State and Federal processes and to use our tax dollars wisely

After six years of actively participating in these State and Federal processes and with a background in process control engineering, I want to make my following observations perfectly clear:

  • The ODOT Project Development Process and Public Involvement Process- lack timely and factual information; lack true public involvement; and lack transparency in decision making.
  • I am losing all trust and confidence in these processes because of my experiences and treatment while actively participating in these processes.
  • Renewed hope with Governor Strickland beginning to "Turnaround" ODOT with a new director and stating the new leadership will re-examine Cleveland's massive Innerbelt Project.

 REQUESTED SOLUTION- Federal, State, County and City Public Officials must commission a "Peer Review" and hire an independent (unbiased) consultant to conduct a valid engineering study and economic impact study to compare the costs, feasibility, traffic interruptions and economic impact for ODOT's Northern Bridge Alignment and the "original" Southern Bridge Alignment (new two-way bridge)

CONCLUSION- If our public officials choose NOT to commission the "Peer Review" for the Innerbelt Bridge Project stated above, I recommend a "Minimal Build" alternative for the Cleveland Innerbelt Project.  That would entail straightening the Innerbelt Curve ("Dead Man's Curve") at $98 million and rehabilitate the existing Innerbelt Bridge for 50 years at $268 million for a total cost to the taxpayers of $366 million.  That would save the taxpayers $1.134 BILLION ($1.5B-$366M) that could be used elsewhere.  The citizens and taxpayers of Ohio cannot accept substandard state and federal processes that yield substandard outcomes!